| Danya-Cebus constructed the frame of the Intel Fab project at Kiryat Gat - the world largest chips production FAB of Intel International. Total area of the three floors of the building is 72,000 square meters (24,000 m2 per floor - equal to the area of five football fields), with about 1,300 pillars in each floor. The unique type and size of this project make it one of the largest engineering projects ever constructed in Israel. At its peak, about 870 employees were employed 24/7 in its construction. The project construction was completed within 7 months only. The German M+W ZANDER acted as the project management company. Total project cost for Intel exceeded $4 billion. Entrepreneur: Intel Architect:Ilan Eldar Architects Construction: Dickman Horovitz Buch Supervision: M+W ZANDER ISRAEL Building Method: Conventional |
|
|